Lucia Fan
Business post
Custom CNC Machined Stainless Steel Pressure Housings & Tubular Parts for Subsea / Marine Applications
Check out this big beast! These are parts ordered by our customer for his subsea project. How many working days will it take to complete these parts? Below is our procedure and timeline (stainless tube blanks are available): ✅ Programming & fixture setup: 0.5 day ✅ Rough & finish turning (OD & ID): 1 day ✅ 4-axis milling: hole drilling, flange milling, boss & mounting seat machining: 1.5 days ✅ Boss welding + post-weld stress relieving: 1 day ✅ Rework machining on welded areas, polishing, deburring & dimensional inspection: 1 day ✅ Final passivation treatment: 1 day Total: 6 working days
Dinnava